` Phoenix Temple Master Plan  
Phoenix Temple Master Plan

Home  |  Donate  |  Pledge Form  |  Phoenix Temple History  |  Master Plan Timeline  |  Architectural Plan
Phoenix Temple Master Plan
Master Plan Timeline
Master Plan and Fellowship Hall Update History:
September 2017 Dedication of the new Fellowship Hall.
August 2017 The stucco work is done and the scaffolding down
July 2017 Closing in the main hall, center section of the building, installing windows
May 2017 Second floor walls going up
March 2017 Walls are started
March 14, 2017 Foundation complete
March 6, 2017 Placement of prayer cards in the foundation
January 8, 2017 Groundbreaking for the Fellowship Hall
April 2016 Received approval from Mother Center to complete construction drawings.
June 2015 Received formal approval from Mother Center to commence next phases of architectural design and permitting.
March 31, 2015 Presented our project to the General Managers Group at Mother Center and received unanimous support.
November 23, 2014 Fundraising Campaign continues with presentation to congregation
November 9, 2014 Architect presents final schematic design to congregation, with preliminary budget of $2.5 million (expected to be high water mark); receives 100% approval
November 2014 Schematic Design reviewed with SRF Planning & Building Dept, receives favorable comments from both Planning & Building & Brother Vishwananda. Formal presentation to SRF Board of Directors planned for late January 2015
October 2014 Schematic Design completed
September 2014 General Contractor hired for pre-construction services--Concord
August 2014 "Master Planning Weekend": The architect meets with all the user groups
July 2014 "Schematic Design" process begins (determining what will be built, in what footprint it will be built, and what the general floor plan of the building will be)
June 2014 Architect hired--Paul Ladensack of CCBG Architects.
May 2014 Project Manager identified: Chris Carroll
Feb 2014 Received approval of SRF Management to engage an architect and contractor for schematic plan and budget
March 2013 Presented proposed process to congregation and received 98.2% support
Summer 2012-Spring 2013 Expansion committee formed to reassess needs & identify new direction
2011-2012 Learned 2nd Street property NOT available - Master Plan needed to be revised
2010-2012 Fund drive was undertaken / approximately $1.2 million were donated to buy adjacent properties
2010 SRF Management approved 5 phase Phoenix Temple Master Plan developed under Brother Ritananda

Copyright © 2015 Self-Realization Fellowship. All rights reserved.
Last updated: 09/03/2019 12:13:59 AM


TOP